The Ground Penetrating Radar (GPR) is frequently used in pavement engineering
for road pavement inspection. The main objective of this work is to validate
nondestructive, quick and powerful measurements using GPR for assessment of subgrade
and asphalt /concrete conditions. In the present study, two different antennas
(250, 500 MHz) were used. The case studies are presented was carried in University
of Baghdad over about 100m of paved road. After data acquisition and radar grams
collection, they have been processed using RadExplorer V1.4 software
implementing different filters with the most effective ones (time zero adjustment and
DC removal) in addition to other interpretation tool parameters.
The interpretation results showed that with 250 MHz antenna, the buried plastic pipe
and the flexible pavement layer were identified. The later appeared as one layer
without identifying the rigid pavement layer. With 500 MHz antenna, the plastic
pipe, rigid pavement, appeared clearly. Moreover, the short type of maximum time
window using antenna 500 MHz appeared to be the most suitable for detecting some
radar anomalies (plastic pipe, and pavement thickness) which were clearly defined.
While, the suitable radar wave velocity was 100 m/ns for estimation of the flexible
and rigid pavement layer thicknesses respectively. No change is obtained with
changing point interval. . Finally, this diagnostic tool of GPR for pavement defects
and damages investigations seems very promising, cost effective and efficient in its
implementation.
Current numerical research was devoted to investigating the effect of castellated steel beams without and with strengthening. The composite concrete asymmetrical double hot rolled steel channels bolted back to back to obtain a built-up I-shape form are used in this study. The top half part of the steel is smaller than the bottom half part, and the two parts were connected by bolting and welding. The ABAQUS/2019 program employed the same length and conditions of loading for four models: The first model is the reference without castellated and strengthening; the second model was castellated without strengthened; the third model was castellated and strengthened with reactive powder concrete encased in the
... Show MoreThis study reveals the results of a numerical simulation performed using the ABAQUS/CAE finite element program. The study aimed to provide a simulation model that can forecast the shear behavior of reinforced concrete beams confined with reinforcing meshes. Limited numerical studies have been conducted using geogrid or FRP mesh as shear reinforcement, with limited representation accuracy and limited material quality. The results were compared to published experimental findings in the literature. The finding of the finite element model and the experimental results were highly comparable; consequently, the model was determined to be valid. Following this, the domain of numerical analyses was broadened to include the investigation of m
... Show MoreSustainable pavements are pavements that meet the requirements of present generation without influencing the capability of the future generation to meet their needs. One of the problems of the warm mix asphalt is that it has low resistance to moisture damage; therefore, the aim of this research paper is to study the possibility of producing more durable warm mixes against the moisture damage with the use of recycled concrete aggregate (RCA) which has not been studied before. Six replacement rates (0, 20, 40, 60, 80, and 100%) for the coarse version aggregate (VA) with RCA were studied. The Marshall mix design method was used to determine the optimum asphalt cement content for each replacement rate. Thereafter, specimens with the opt
... Show MoreSustainable pavements are pavements that meet the requirements of present generation without influencing the capability of the future generation to meet their needs. One of the problems of the warm mix asphalt is that it has low resistance to moisture damage; therefore, the aim of this research paper is to study the possibility of producing more durable warm mixes against the moisture damage with the use of recycled concrete aggregate (RCA) which has not been studied before. Six replacement rates (0, 20, 40, 60, 80, and 100%) for the coarse version aggregate (VA) with RCA were studied. The Marshall mix design method was used to determine the optimum asphalt cement content for each replacement rate. Thereafter, specimens with the opt
... Show MoreThis research deals with unusual approach for analyzing the Simple Linear Regression via Linear Programming by Two - phase method, which is known in Operations Research: “O.R.”. The estimation here is found by solving optimization problem when adding artificial variables: Ri. Another method to analyze the Simple Linear Regression is introduced in this research, where the conditional Median of (y) was taken under consideration by minimizing the Sum of Absolute Residuals instead of finding the conditional Mean of (y) which depends on minimizing the Sum of Squared Residuals, that is called: “Median Regression”. Also, an Iterative Reweighted Least Squared based on the Absolute Residuals as weights is performed here as another method to
... Show More
In this work, a test room was built in Baghdad city, with (2*1.5*1.5) m3 in dimensions, while the solar chimneys (SC) were designed with aspect ratio (ar) bigger than 12. Test room was supplied by many solar collectors; vertical single side of air pass with ar equals 25, and tilted 45o double side of air passes with ar equals 50 for each pass, both collectors consist of flat thermal energy storage box collector (TESB) that covered by transparent clear acrylic sheet, third type of collector is array of evacuated tubular collectors with thermosyphon in 45o instelled in the bottom of TESB of vertical SC. The TESB was
... Show More